Week of July 27 — July 31, 2026
5 days on site. 29 photos. Cabinets, Electric, Landscape, Plumbing, Site Concrete and Drainage, Stucco, Windows.
Monday, July 27, 2026
Clear, 81°F
NOTES: ZSP finishing water heaters, walked cutting down clean outs and lowering the shut off in front yard for the landscaping.
JBG continuing fencing
Marq Plastering completing stucco work on existing houses.
Golden Roots continuing landscape.
Primera completing minor touch ups and review of issues with Michael F.
Ac elec - pulling wires
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Marq Plastering | 1 | 8 | 8 |
| AC Electric | 3 | 8 | 24 |
| JB General | 3 | 8 | 24 |
| Golden Roots | 4 | 8 | 32 |
| Primera | 1 | 3 | 3 |
| Zack Smith Plumbing | 1 | 8 | 8 |
INSPECTIONS: n/a
VISITORS: n/a
SAFETY INCIDENTS: n/a
DELAYS: n/a







Tuesday, July 28, 2026
Partially cloudy, 73°F
AC Electric pulling wire for power to new units
JB General installing posts
Golden Roots grading soil and installing plants and trees.
ZSP Plumbing installing valve box for water line in front yard and cutting pipes to grade.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| AC Electric | 3 | 8 | 24 |
| ZSP Plumbing | 2 | 8 | 16 |
| Golden Roots Landscaping | 4 | 8 | 32 |
| JB General | 3 | 8 | 24 |
Inspection: ---





Wednesday, July 29, 2026
Clear, 79°F
Cleaners onsite to clean all units
Landscapers continuing to install plants
Marq patching stucco
JB General installing posts and fencing
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JB General | 1 | 8 | 8 |
| Marq | 2 | 8 | 16 |
| Golden Roots | 10 | 8 | 80 |
| Refined Rennovations | 3 | 8 | 24 |
Inspection: ---





Thursday, July 30, 2026
Clear, 79°F
Marq taping windows and prepping for fog cutting
JB General installing window into existing duplex
Golden Roots grading and compacting front yard
ZSP clean up work inside units
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JB General | 1 | 8 | 8 |
| Marq | 4 | 8 | 32 |
| General Roots | 3 | 8 | 24 |
| ZSP | 1 | 4 | 4 |
Inspection: ---








Friday, July 31, 2026
Clear, 81°F
Golden Roots continuing landscaping
ZSP installing hose bibs and finishing condensate drains.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| ZSP | 1 | 8 | 8 |
| Golden Roots | 4 | 8 | 32 |
| Clear HVAC | 2 | 1 | 2 |
Inspection: ---