Week of July 27 — July 31, 2026

5 days on site. 29 photos. Cabinets, Electric, Landscape, Plumbing, Site Concrete and Drainage, Stucco, Windows.

July 27, 2026July 31, 20265 days29 photos
CabinetsElectricLandscapePlumbingSite Concrete and DrainageStuccoWindows

Monday, July 27, 2026

Clear, 81°F

NOTES: ZSP finishing water heaters, walked cutting down clean outs and lowering the shut off in front yard for the landscaping.

JBG continuing fencing

Marq Plastering completing stucco work on existing houses.

Golden Roots continuing landscape.

Primera completing minor touch ups and review of issues with Michael F.

Ac elec - pulling wires


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Marq Plastering188
AC Electric3824
JB General3824
Golden Roots4832
Primera133
Zack Smith Plumbing188

INSPECTIONS: n/a


VISITORS: n/a


SAFETY INCIDENTS: n/a


DELAYS: n/a

image.jpg

image.jpg

image.jpg

image.jpg

image.jpg

image.jpg

image.jpg


Tuesday, July 28, 2026

Partially cloudy, 73°F

AC Electric pulling wire for power to new units

JB General installing posts

Golden Roots grading soil and installing plants and trees.

ZSP Plumbing installing valve box for water line in front yard and cutting pipes to grade.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
AC Electric3824
ZSP Plumbing2816
Golden Roots Landscaping4832
JB General3824

Inspection: ---

0170d2fe-247c-4961-b74a-cbede68d710d.jpg.jpeg

95fca25a-0b3c-483a-b51c-1ebc35e90887.jpg.jpeg

5f3e6956-7228-4cac-8604-b6bdf0512f16.jpg.jpeg

20585.jpg.jpeg

0da4c0dc-e021-4185-bdad-96a68c862437.jpg.jpeg


Wednesday, July 29, 2026

Clear, 79°F

Cleaners onsite to clean all units

Landscapers continuing to install plants

Marq patching stucco

JB General installing posts and fencing


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General188
Marq2816
Golden Roots10880
Refined Rennovations3824

Inspection: ---

83624faa-48e3-4e64-a94d-65d004921a47.jpg.jpeg

e334ce75-9886-43b5-ac0a-fa20fa54923a.jpg.jpeg

7cb1ece1-1e49-4dab-97a5-6b702dda58c1.jpg.jpeg

44838424-c6d0-4e69-93a6-2411ada26622.jpg.jpeg

73ed487e-ec9f-4b97-aa03-2343c35363e3.jpg.jpeg


Thursday, July 30, 2026

Clear, 79°F

Marq taping windows and prepping for fog cutting

JB General installing window into existing duplex

Golden Roots grading and compacting front yard

ZSP clean up work inside units


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General188
Marq4832
General Roots3824
ZSP144

Inspection: ---

20260730_120732.jpg

20260730_121435.jpg

20260730_120702.jpg

20260730_120719.jpg

20260730_120607.jpg

20260730_120633.jpg

20260730_121621.jpg

20260730_124931.jpg


Friday, July 31, 2026

Clear, 81°F

Golden Roots continuing landscaping

ZSP installing hose bibs and finishing condensate drains.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
ZSP188
Golden Roots4832
Clear HVAC212

Inspection: ---

20260731_124636.jpg

20260731_124717.jpg

20260731_124620.jpg

20260731_124630.jpg