Week 31 of 34

Week of July 20 — July 24, 2026

5 days on site. 34 photos. Earthwork, Electric, HVAC, Inspection, Paint, Plumbing, Site Concrete and Drainage.

July 20, 2026July 24, 20265 days34 photos
EarthworkElectricHVACInspectionPaintPlumbingSite Concrete and Drainage

Monday, July 20, 2026

Clear, 71°F

Painters Unlimited paintings walls and ceilings at Building B2.

Clear HVAC getting outdoors units delivered and starting install.

ZSP continuing to test fixtures at all units and finish trim out.

AC Electric finishing meter labeling and preparing for inspection today.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Painters Unlimited2816
ZSP144
AC Electric122
Clear HVAC4832

Inspection: Danny S. on site at 11:40 AM. Signed off on meter at all units.


IMG_4502.jpeg

IMG_4510.jpeg

IMG_4505.jpeg

IMG_4512.jpeg

IMG_4511.jpeg


Tuesday, July 21, 2026

Clear, 81°F

JBG installing rebar and forms for remaining site concrete.

AC Electric installing exterior equipment.

Painters Unlimited working on Building B interiors.

Clear HVAC installing ducts and other pick-up items.

ML left voicemail with SDGE.

Guillermo from TT on site to look at cracked pocket door.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JBG3824
AC Electric188
Clear HVAC2816
Painters Unlimited3824

Inspection: N/A


IMG_4571.jpeg

IMG_4570.jpeg

IMG_4569.jpeg

IMG_4557.jpeg

IMG_4535.jpeg

IMG_4533.jpeg

IMG_4534.jpeg

IMG_4531.jpeg

IMG_4532.jpeg


Wednesday, July 22, 2026

Partially cloudy, 76°F

JBG on site this AM to finish rebar and formwork. Ready to pour tomorrow.

Painters Unlimited painting garage conversion wall and ceilings and then touching up baseboards and doors in all units.

ZSP backfilling trench, installing tankless water heater and adjusting trim out.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JBG3412
Painters Unlimited3824
ZSP188

Inspection: Ryan Bailey (Eco Green Energy) on site at 11:00 AM for HERs inspection. No issues. He will work on report.


IMG_4605.jpeg

IMG_4607.jpeg

IMG_4602.jpeg

IMG_4606.jpeg

IMG_4600.jpeg

IMG_4601.jpeg

IMG_4597.jpeg

IMG_4598.jpeg

20260722_144518.jpg

20260722_144524.jpg


Thursday, July 23, 2026

Clear, 81°F

JBG pouring concrete for sidewalk and stairs today.

Painters unlimited painting water heater enclosures.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General3515
Painters Unlimited2412

Inspection: ---

20260723_155404.jpg

20260723_155542.jpg

20260723_140246.jpg

20260723_140015.jpg

20260723_140218.jpg

20260723_140240.jpg


Friday, July 24, 2026

Clear, 80°F

ZSP installing and testing water heater

JBG hauling off excess dirt from front yard.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JBG2612
ZSP188

Inspection: ---

20260724_141539.jpg

20260724_141836.jpg

20260724_141546.jpg

20260724_141740.jpg