Week 33 of 34

Week of August 03 — August 07, 2026

4 days on site. 12 photos. Delay, Gutters, Landscape, Paint, Stucco.

August 3, 2026August 7, 20264 days12 photos
DelayGuttersLandscapePaintStucco

Monday, August 03, 2026

Clear, 80°F

JB General installing fencing

ZSP doing final trim, clean up work.

Painters unlimited onsite to pressure wash exterior.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General3824
ZSP248
Painters Unlimited212

Inspection: ---

Delay: Marq had work call out sick. Stucco patch on existing duplex and paint are being pushed 2 days. Stucco patch eta tomorrow, paint will begin Wednesday.

20260803_124216.jpg

20260803_124150.jpg


Wednesday, August 05, 2026

Partially cloudy, 80°F

Painters unlimited onsite to paint exterior of existing building.

Trash pickup for majority of dunnage onsite.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Painters unlimited3824

Inspection: ---

20260805_125450.jpg

20260805_125504.jpg

20260805_125506.jpg


Thursday, August 06, 2026

Partially cloudy, 80°F

Painters onsite painting existing duplex.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Painters Unlimited336

Inspection: ---

20260806_115220.jpg

20260806_113133.jpg

20260806_113159.jpg


Friday, August 07, 2026

Clear, 82°F

Aquasol onsite installing gutters


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Aquasol248

Inspection: ---

20260807_131546.jpg

20260807_131618.jpg

20260807_131444.jpg

20260807_131505.jpg