Week 33 of 34
Week of August 03 — August 07, 2026
4 days on site. 12 photos. Delay, Gutters, Landscape, Paint, Stucco.
August 3, 2026 — August 7, 20264 days12 photos
DelayGuttersLandscapePaintStucco
Monday, August 03, 2026
Clear, 80°F
JB General installing fencing
ZSP doing final trim, clean up work.
Painters unlimited onsite to pressure wash exterior.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JB General | 3 | 8 | 24 |
| ZSP | 2 | 4 | 8 |
| Painters Unlimited | 2 | 1 | 2 |
Inspection: ---
Delay: Marq had work call out sick. Stucco patch on existing duplex and paint are being pushed 2 days. Stucco patch eta tomorrow, paint will begin Wednesday.


Wednesday, August 05, 2026
Partially cloudy, 80°F
Painters unlimited onsite to paint exterior of existing building.
Trash pickup for majority of dunnage onsite.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Painters unlimited | 3 | 8 | 24 |
Inspection: ---



Thursday, August 06, 2026
Partially cloudy, 80°F
Painters onsite painting existing duplex.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Painters Unlimited | 3 | 3 | 6 |
Inspection: ---



Friday, August 07, 2026
Clear, 82°F
Aquasol onsite installing gutters
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Aquasol | 2 | 4 | 8 |
Inspection: ---