Week of July 06 — July 10, 2026
5 days on site. 55 photos. Cabinets, Electric, Paint, Plumbing, Site Concrete and Drainage, Stucco, Traffic Coating.
Monday, July 06, 2026
Clear, 74°F
JBG continuing formwork for site concrete at Building C and between the buildings.
AC Electric continuing trim out and other pick up items.
ZSP continuing trim out.
Painters Unlimited painting exterior doors.
ML walked site with Ken Huffman (Traditions Drywall) to discuss punchlist items.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| ZSP | 1 | 8 | 8 |
| AC Electric | 1.5 | 8 | 12 |
| JBG | 5 | 8 | 40 |
| Painters Unlimited | 1 | 4 | 4 |
Inspection: N/A
Delay: Electrical issue (city/SDGE)













Tuesday, July 07, 2026
Clear, 73°F
Primera completing pick up items.
JBG continuing to form site concrete.
ZSP trimming out.
AC Electric trimming out.
Marq finishing stucco at garage.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Primera | 1 | 8 | 8 |
| JBG | 6 | 8 | 48 |
| Marq | 2 | 8 | 16 |
| AC Electric | 0.5 | 8 | 4 |
| ZSP | 1 | 8 | 8 |
Inspection: N/A
Delay: Pending City review and SDGE response









Wednesday, July 08, 2026
Clear, 74°F
JBG installing rebar and preparing for concrete pour (pushed to Saturday). Laying out fence along back property line. Discussed how to get water heaters installed at Unit B without blocking off access for possible SDGE underground conduit. Wing wall to be eliminated and water heater enclosure to be be primed and painted to match color of siding. Pad for water heaters to be poured on Saturday, so plumbing can be finished.
ZSP continuing to trim out units.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JBG | 4 | 8 | 32 |
| ZSP | 1 | 8 | 8 |
Inspection: N/A
Delay: Pending city comments, SDGE response, response from Gino to plea for accommodation.












Thursday, July 09, 2026
Partially cloudy, 72°F
ZSP roughing in and preparing for site concrete pour.
JBG installing back fence and finishing rebar/formwork.
Rete's putting down first coat of final before color coat.
Marq plastering on site to look at existing stucco again. Demoing lower 18" of wall between existing duplex and Building B tomorrow. Creating plan to demo and patch as needed at existing duplex (after meter release).
ML cleaning up units.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| ZSP | 1 | 8 | 8 |
| JBG | 3 | 8 | 24 |
| Rete's | 2 | 4 | 8 |
Inspection: N/A
Delay: Pending response from Gino.














Friday, July 10, 2026
Overcast, 68°F
Marq on site chipping stucco at existing duplex.
Rete's putting final coat on stairs at B and C.
Brent (JBG) on site to confirm everything is ready for tomorrow’s pour.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Marq | 1 | 4 | 4 |
| Rete’s | 2 | 2 | 4 |
Inspection: N/A
Delay: Sam is doing calcs. Pending response from SDGE re 420 A calc.