Week of June 29 — July 02, 2026
4 days on site. 69 photos. Countertops, DFH, Drywall, Electric, Inspection, Plumbing, Site Concrete and Drainage, Stucco.
Monday, June 29, 2026
Partially cloudy, 70°F
AC Electric trimming garage unit.
JBG installing drains.
Taylor Trim installing baseboard at C2 and B2.
Marq Plastering installing seismic joint at front site between garage and duplex.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| AC Electric | 1.5 | 8 | 12 |
| JBG | 4 | 8 | 32 |
| Taylor Trim | 1 | 8 | 8 |
| Marq | 1 | 4 | 4 |
Inspection: N/A



















Tuesday, June 30, 2026
Partially cloudy, 62°F
AC Electric continuing trim out.
Marjan installing countertops. Garage kitchen countertops pending sink.
JBG installing drains, backfilling and starting formwork.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| AC Electric | 1 | 8 | 8 |
| JBG | 4 | 8 | 32 |
| Marjan Stone | 4 | 8 | 32 |
Inspection: N/A
Delay: Electric saga with the city continues…










Wednesday, July 01, 2026
Partially cloudy, 68°F
AC Electric continuing trim.
ZSP continuing trim.
JBG finishing up drainage and working on formwork for raised entrance at building C.
Taylor Trim installing bathroom hardware and interior door hardware.
Marjan on site at 2:30 pm to do garage countertops.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JBG | 6 | 8 | 48 |
| AC Electric | 4 | 8 | 32 |
| ZSP | 1 | 8 | 1 |
| Taylor Trim | 2 | 8 | 16 |
Inspection: Dave Finney on site at 2:30 pm. Passed lath and plaster at garage.
Delay: Electrical submittal
















Thursday, July 02, 2026
Overcast, 66°F
Marq stuccoing garage.
AC Electric installing ceiling fans and doorbells.
ZSP installing garbage disposals and faucets.
JBG forming site concrete on building C side.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Marq | 6 | 8 | 48 |
| JBG | 4 | 8 | 32 |
| AC Electric | 2 | 8 | 16 |
| ZSP | 1 | 8 | 8 |
Inspection: N/A
Delay: Pending informal review of electrical plans and SDGE estimated cost / schedule impacts for transformer.