All updates
Week 28 of 34

Week of June 29 — July 02, 2026

4 days on site. 69 photos. Countertops, DFH, Drywall, Electric, Inspection, Plumbing, Site Concrete and Drainage, Stucco.

June 29, 2026July 2, 20264 days69 photos
CountertopsDFHDrywallElectricInspectionPlumbingSite Concrete and DrainageStucco

Monday, June 29, 2026

Partially cloudy, 70°F

AC Electric trimming garage unit.

JBG installing drains.

Taylor Trim installing baseboard at C2 and B2.

Marq Plastering installing seismic joint at front site between garage and duplex.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
AC Electric1.5812
JBG4832
Taylor Trim188
Marq144

Inspection: N/A


IMG_3499.jpeg

IMG_3489.jpeg

IMG_3490.jpeg

IMG_3501.jpeg

IMG_3500.jpeg

IMG_3503.jpeg

IMG_3502.jpeg

IMG_3504.jpeg

IMG_3505.jpeg

IMG_3507.jpeg

IMG_3506.jpeg

IMG_3527.jpeg

IMG_3508.jpeg

IMG_3529.jpeg

IMG_3528.jpeg

IMG_3531.jpeg

IMG_3533.jpeg

IMG_3537.jpeg

IMG_3538.jpeg


Tuesday, June 30, 2026

Partially cloudy, 62°F

AC Electric continuing trim out.

Marjan installing countertops. Garage kitchen countertops pending sink.

JBG installing drains, backfilling and starting formwork.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
AC Electric188
JBG4832
Marjan Stone4832

Inspection: N/A


Delay: Electric saga with the city continues…

IMG_3555.jpeg

IMG_3550.jpeg

IMG_3557.jpeg

IMG_3556.jpeg

IMG_3560.jpeg

IMG_3559.jpeg

IMG_3565.jpeg

IMG_3561.jpeg

IMG_3567.jpeg

IMG_3566.jpeg


Wednesday, July 01, 2026

Partially cloudy, 68°F

AC Electric continuing trim.

ZSP continuing trim.

JBG finishing up drainage and working on formwork for raised entrance at building C.

Taylor Trim installing bathroom hardware and interior door hardware.

Marjan on site at 2:30 pm to do garage countertops.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JBG6848
AC Electric4832
ZSP181
Taylor Trim2816

Inspection: Dave Finney on site at 2:30 pm. Passed lath and plaster at garage.


Delay: Electrical submittal

IMG_3649.jpeg

IMG_3653.jpeg

IMG_3647.jpeg

IMG_3648.jpeg

IMG_3644.jpeg

IMG_3646.jpeg

IMG_3641.jpeg

IMG_3642.jpeg

IMG_3634.jpeg

IMG_3639.jpeg

IMG_3630.jpeg

IMG_3631.jpeg

IMG_3624.jpeg

IMG_3629.jpeg

IMG_3613.jpeg

IMG_3622.jpeg


Thursday, July 02, 2026

Overcast, 66°F

Marq stuccoing garage.

AC Electric installing ceiling fans and doorbells.

ZSP installing garbage disposals and faucets.

JBG forming site concrete on building C side.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Marq6848
JBG4832
AC Electric2816
ZSP188

Inspection: N/A


Delay: Pending informal review of electrical plans and SDGE estimated cost / schedule impacts for transformer.

IMG_3689.jpeg

IMG_3690.jpeg

IMG_3695.jpeg

IMG_3694.jpeg

IMG_3700.jpeg

IMG_3698.jpeg

IMG_3701.jpeg

IMG_3703.jpeg

IMG_3705.jpeg

IMG_3704.jpeg

IMG_3707.jpeg

IMG_3706.jpeg

IMG_3728.jpeg

IMG_3708.jpeg

IMG_3731.jpeg

IMG_3729.jpeg

IMG_3735.jpeg

IMG_3732.jpeg

IMG_3737.jpeg

IMG_3736.jpeg

IMG_3018.jpeg

IMG_3734.jpeg

IMG_3019.jpeg

IMG_3017.jpeg