Week 27 of 34

Week of June 22 — June 26, 2026

5 days on site. 50 photos. Cabinets, Countertops, Electric, Flooring, Paint, Plumbing, Roofing, Site Concrete and Drainage, Solar, Tile.

June 22, 2026June 26, 20265 days50 photos
CabinetsCountertopsElectricFlooringPaintPlumbingRoofingSite Concrete and DrainageSolarTile

Monday, June 22, 2026

Clear, 72°F

JBG continuing to move dirt and clean up the jobsite.

Primera installing cabinets.

Coastal finishing Niche and installing schluter metal at Garage bathroom. Grout tomorrow.

Taylor Trim installing doors at garage and bifolds at Unit B.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Coastal188
JBG3824
Primera3824
Taylor Trim144

Inspection: N/A


Delay: Pending response form Gino ( DSD)

IMG_3162.jpeg

IMG_3160.jpeg

IMG_3163.jpeg

IMG_3161.jpeg

IMG_3178.jpeg

IMG_3174.jpeg

IMG_3180.jpeg

IMG_3179.jpeg

IMG_3182.jpeg

IMG_3181.jpeg

IMG_3184.jpeg

IMG_3183.jpeg

IMG_3186.jpeg

IMG_3185.jpeg


Tuesday, June 23, 2026

Partially cloudy, 72°F

JBG moving dirt and prepping drainage elevations.

ZSP adjusting gas line for roofers.

Painters Unlimited painting siding and garage interior.

Coastal installing LVP at B2, C2, and D. Grouting garage shower.

Primera on site doing QC checks.

Sunline installing wall equipment on Building C. Solar panels delivered at 11:05 AM.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JBG5840
ZSP2816
Painters Unlimited4832
Coastal - Flooring Crew7428
Coastal - Tiler166
Primera248

Inspection: N/A


Delay: Pending calculations from Flores and path forward. Temp power pole in way of site concrete near Building B. Waiting on Building B site concrete in case we need to underground to transformer.

IMG_3224.jpeg

IMG_3220.jpeg

IMG_3225.jpeg

IMG_3221.jpeg

IMG_3229.jpeg

IMG_3228.jpeg

IMG_3231.jpeg

IMG_3230.jpeg

IMG_3234.jpeg

IMG_3233.jpeg

IMG_3236.jpeg

IMG_3235.jpeg

IMG_3238.jpeg

IMG_3237.jpeg

IMG_3240.jpeg

IMG_3239.jpeg


Wednesday, June 24, 2026

Partially cloudy, 72°F

JBG on site continuing to prep for drainage install.

Roofers installing flashing over seismic gap between existing duplex and garage.

Coastal installing LVP at garage.

Marjan Stone templating countertops for fabrication.

Sunline installing panels on Buildings B and C.

ML completed preliminary blue tape walk and alerted drywallers, cabinets, and DFH of corrections needed.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Coastal2510
JBG4840
ACCI3412

Inspection: N/A


Delay: Meter saga continuines....

IMG_3283.jpeg

IMG_3299.jpeg

IMG_3288.jpeg

IMG_3305.jpeg

IMG_3303.jpeg


Thursday, June 25, 2026

Clear, 71°F

AC Electric installing LED lights and finish.

ACCI finishing roof repair at existing duplex.

JBG finalizing rough grade and drainage mat at Building B.

Sunline on site.

Coastal laying out C2 bathroom floor tile.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JBG2816
ACCI3515
AC Electric3824

Coastal - 1 - 8 - 8


Inspection: N/A


Delay: Pending final calcs from Sam (Flores)

IMG_3356.jpeg

IMG_3355.jpeg

IMG_3354.jpeg

IMG_3358.jpeg

IMG_3359.jpeg

IMG_3370.jpeg

IMG_3371.jpeg

IMG_3368.jpeg

IMG_3369.jpeg


Friday, June 26, 2026

Clear, 72°F

JBG General digging trenches for solid drains.

Coastal finishing C2 bathroom floor layout.

TDI on site to walk through items that need correcting.

AC Electric roughing in units and exterior lighting.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
AC Electric3824
JBG2.5820

Inspection: N/A


IMG_3359.jpeg

IMG_3358.jpeg

IMG_3371.jpeg

IMG_3368.jpeg

IMG_3369.jpeg

IMG_3370.jpeg