All updates
Week 26 of 34

Week of June 15 — June 20, 2026

6 days on site. 59 photos. Cabinets, DFH, Drywall, Gutters, Paint, Plumbing, Scaffolding, Siding, Site Concrete and Drainage, Solar, Stucco, Tile.

June 15, 2026June 20, 20266 days59 photos
CabinetsDFHDrywallGuttersPaintPlumbingScaffoldingSidingSite Concrete and DrainageSolarStuccoTile

Monday, June 15, 2026

Clear, 73°F

Coastal grouting shower walls at C2 and laying out shower floor tile.

TT installing remaining interior doors. Bi-folds to be installed after paint. Baseboards installed at B1 and C1, in areas with no cabinets.

Marq papering areas for siding.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Marq188
Coastal188
Taylor Trim2816

Inspection: Dave Finney on site at 10:50 for drywall screw inspection at Garage Conversion. Passed!


Delay: Electrical load issue has not been resolved with the city. 1070 still working on it. We will be ready to schedule SDGE electrification on Wednesday, when scaffolding comes down.

IMG_2896.jpeg

IMG_2893.jpeg

IMG_2894.jpeg

IMG_2891.jpeg

IMG_2892.jpeg

IMG_2877.jpeg

IMG_2880.jpeg

IMG_2868.jpeg

IMG_2876.jpeg

IMG_2866.jpeg

IMG_2863.jpeg

IMG_2861.jpeg

IMG_2865.jpeg

IMG_2859.jpeg

IMG_2860.jpeg


Tuesday, June 16, 2026

Clear, 74°F

Aquasoltech installing gutters and downspouts on B and C.

Marq fogcoating and cleaning at B&C and installing paper, foam and lath at the garage.

Painters Unlimited priming and painting first coat at B and C.

TDI taping garage.

Coastal waterproofing garage shower walls.

Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Aquasoltech2816
Marq5840
Painters Unlimited4832
TDI5420

Coastal - 1 worker, 4 hours


Inspection: N/A


Delay: Call with 1070, Flores, and Michael Walker, regarding electrical delay. Sean (1070) and Sam (Flores) working on scheduling a meeting with Gino (Assistant Deputy Director, City of San Diego).

IMG_2991.jpeg

![IMG_0231 - 2.jpeg](/photos/2026-06-16/IMG_0231 - 2.jpeg)

IMG_0232.jpeg

![IMG_2984 - 1.jpeg](/photos/2026-06-16/IMG_2984 - 1.jpeg)

IMG_2985.jpeg

IMG_2980.jpeg

![IMG_2983 - 1.jpeg](/photos/2026-06-16/IMG_2983 - 1.jpeg)

IMG_2970.jpeg

![IMG_2979 - 1.jpeg](/photos/2026-06-16/IMG_2979 - 1.jpeg)

![IMG_2968 - 1.jpeg](/photos/2026-06-16/IMG_2968 - 1.jpeg)

![IMG_2969 - 1.jpeg](/photos/2026-06-16/IMG_2969 - 1.jpeg)

IMG_2962.jpeg

IMG_2967.jpeg

IMG_2931.jpeg

IMG_2933.jpeg

IMG_2928.jpeg

IMG_2929.jpeg

IMG_2926.jpeg

IMG_2927.jpeg


Wednesday, June 17, 2026

Partially cloudy, 73°F

Coastal laying out wall tile at garage conversion shower.

ZSP relocating water lines between garage and existing duplex.

Marq installing siding at B and C.

Scaffolding coming down.

TDI patching drywall cuts at kitchen.

Painters unlimited continuing to paint B and C.

Sunline on site, continuing to install solar equipment.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Coastal188
ZSP144
Marq2816
Painters Unlimited4832
TDI144


Inspection: N/A


Delay: Meeting with Gino and Margaret Q (DSD) did not produce any resolution. Gino and Sam (Flores Engineering) to have follow up discussion tomorrow at 2 to review a different code section.

IMG_3029.jpeg

IMG_3026.jpeg

IMG_3027.jpeg

IMG_3018.jpeg

IMG_3022.jpeg

IMG_3016.jpeg

IMG_3017.jpeg

IMG_3012.jpeg

IMG_3013.jpeg

IMG_3007.jpeg

IMG_3010.jpeg

IMG_3004.jpeg

IMG_3005.jpeg

IMG_3021.jpeg


Thursday, June 18, 2026

Overcast, 64°F

Marq Plastering loading all spoils into dumpster. Installing siding at Structure C, second floor.

Coastal continuing to work on tile at garage conversion.

Painters Unlimited touching up paint/sanding in B and C and painting doors.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Marq4832
Coastal181
Painters Unlimited2816

Inspection: N/A


IMG_3054.jpeg

IMG_3055.jpeg

IMG_3062.jpeg

IMG_3053.jpeg

IMG_3065.jpeg

IMG_3064.jpeg

IMG_3068.jpeg

IMG_3066.jpeg


Friday, June 19, 2026

Clear, 72°F

Site shut down for Juneteenth.

Cabinets delivered to site.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS

Inspection: N/A


IMG_3102.jpeg

IMG_3098.jpeg

IMG_3093.jpeg


Saturday, June 20, 2026

Clear, 72°F

Marq Plastering continuing to clean up spoils.

JBG moving dirt and cleaning up to prepare for drainage installation.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Marq2816
JBG2816

Inspection: N/A