Week 25 of 34

Week of June 08 — June 13, 2026

6 days on site. 84 photos. DFH, Drywall, Electric, Paint, Polished Concrete, Solar, Stucco, Tile.

June 8, 2026June 13, 20266 days84 photos
DFHDrywallElectricPaintPolished ConcreteSolarStuccoTile

Monday, June 08, 2026

Clear, 71°F

Marq Plastering color coating Building B and C.

Coastal grouted walls and floors at B1 and C1.

JBG cleaning concrete to prepare for polish.

Window Solutions installed garage windows and changed out pane to tempered glass on B1 window next to door.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Marq6848
JBG188
Coastal248
Window Solutions248

Inspection: N/A


IMG_2575.jpeg

IMG_2574.jpeg

IMG_2577.jpeg

IMG_2576.jpeg

IMG_2579.jpeg

IMG_2578.jpeg

IMG_2581.jpeg

IMG_2580.jpeg

IMG_2584.jpeg

IMG_2582.jpeg

IMG_2586.jpeg

IMG_2588.jpeg

IMG_2587.jpeg

IMG_2589.jpeg

IMG_2592.jpeg

IMG_2591.jpeg


Tuesday, June 09, 2026

Clear, 73°F

Marq plastering patching sections of color coat and cleaning up.

Coastal working on B2 shower. Poured 8 bags of self-levelling in the lower half of the garage. Will return tomorrow to finish. Delta of 1.25" in between low and high spots.

ML mopped B and C slabs to prepare for concrete burnishing and sealing.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Coastal1.5812
Marq3824

Inspection: N/A


IMG_2626.jpeg

IMG_2629.jpeg

IMG_2633.jpeg

IMG_2630.jpeg

IMG_2603.jpeg

IMG_2632.jpeg


Wednesday, June 10, 2026

Clear, 72°F

JBG applying sealant and burnishing B and C concrete floors.

Coastal finishing leveling at garage conversion and continuing wall tile at B2.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JBG2816
Coastal1.5812

Inspection: N/A


IMG_2653.jpeg

IMG_2654.jpeg

IMG_2658.jpeg

IMG_2657.jpeg

1000017655.jpeg

IMG_2655.jpeg

1000017658.jpeg

1000017656.jpeg

Resized_20260610_153950.jpeg

1000017659.jpeg

Resized_20260610_153945.jpeg

Resized_20260610_153954.jpeg


Thursday, June 11, 2026

Partially cloudy, 75°F

Coastal grouting shower wall tile in B2 and starting layout in C2.

AC Electric doing pick up items.

ZSP installing shower pan at Garage.

JBG fixing garage entry door RO.

Sunline installing equipment on Building C wall.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
AC Electric122
Coastal188
JBG122

Inspection: N/A


IMG_2731.jpeg

IMG_2723.jpeg

IMG_2729.jpeg

IMG_2732.jpeg

IMG_2721.jpeg

IMG_2724.jpeg

IMG_2719.jpeg

IMG_2720.jpeg

IMG_2717.jpeg

IMG_2718.jpeg

IMG_2715.jpeg

IMG_2716.jpeg

IMG_2713.jpeg

IMG_2714.jpeg

IMG_2711.jpeg

IMG_2712.jpeg

IMG_2709.jpeg

IMG_2710.jpeg

IMG_2707.jpeg

IMG_2708.jpeg

IMG_2705.jpeg

IMG_2706.jpeg


Friday, June 12, 2026

Clear, 75°F

Painters Unlimited painting drip edge at B&C.

Taylor Trim installing interior door frames and doors at B&C. Baseboard delivered for Monday install.

Coastal working on B2&C2 bathrooms. Targeting Monday completion date.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Coastal2816
Taylor Trim3816
Painters Unlimited144

Inspection: N/A


IMG_2785.jpeg

IMG_2786.jpeg

IMG_2783.jpeg

IMG_2784.jpeg

IMG_2781.jpeg

IMG_2782.jpeg

IMG_2779.jpeg

IMG_2780.jpeg

IMG_2776.jpeg

IMG_2778.jpeg

IMG_2773.jpeg

IMG_2774.jpeg

IMG_2771.jpeg

IMG_2772.jpeg

IMG_2769.jpeg

IMG_2770.jpeg

IMG_2766.jpeg

IMG_2768.jpeg

IMG_2764.jpeg

IMG_2765.jpeg

IMG_2762.jpeg

IMG_2763.jpeg


Saturday, June 13, 2026

Clear, 77°F

TDI hanging drywall at the garage conversion.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
TDI2816

Inspection: N/A


IMG_2871.jpeg

IMG_2870.jpeg

IMG_2873.jpeg

IMG_2872.jpeg

IMG_2875.jpeg

IMG_2874.jpeg