Week of June 08 — June 13, 2026
6 days on site. 84 photos. DFH, Drywall, Electric, Paint, Polished Concrete, Solar, Stucco, Tile.
Monday, June 08, 2026
Clear, 71°F
Marq Plastering color coating Building B and C.
Coastal grouted walls and floors at B1 and C1.
JBG cleaning concrete to prepare for polish.
Window Solutions installed garage windows and changed out pane to tempered glass on B1 window next to door.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Marq | 6 | 8 | 48 |
| JBG | 1 | 8 | 8 |
| Coastal | 2 | 4 | 8 |
| Window Solutions | 2 | 4 | 8 |
Inspection: N/A
















Tuesday, June 09, 2026
Clear, 73°F
Marq plastering patching sections of color coat and cleaning up.
Coastal working on B2 shower. Poured 8 bags of self-levelling in the lower half of the garage. Will return tomorrow to finish. Delta of 1.25" in between low and high spots.
ML mopped B and C slabs to prepare for concrete burnishing and sealing.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Coastal | 1.5 | 8 | 12 |
| Marq | 3 | 8 | 24 |
Inspection: N/A






Wednesday, June 10, 2026
Clear, 72°F
JBG applying sealant and burnishing B and C concrete floors.
Coastal finishing leveling at garage conversion and continuing wall tile at B2.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JBG | 2 | 8 | 16 |
| Coastal | 1.5 | 8 | 12 |
Inspection: N/A












Thursday, June 11, 2026
Partially cloudy, 75°F
Coastal grouting shower wall tile in B2 and starting layout in C2.
AC Electric doing pick up items.
ZSP installing shower pan at Garage.
JBG fixing garage entry door RO.
Sunline installing equipment on Building C wall.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| AC Electric | 1 | 2 | 2 |
| Coastal | 1 | 8 | 8 |
| JBG | 1 | 2 | 2 |
Inspection: N/A






















Friday, June 12, 2026
Clear, 75°F
Painters Unlimited painting drip edge at B&C.
Taylor Trim installing interior door frames and doors at B&C. Baseboard delivered for Monday install.
Coastal working on B2&C2 bathrooms. Targeting Monday completion date.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| Coastal | 2 | 8 | 16 |
| Taylor Trim | 3 | 8 | 16 |
| Painters Unlimited | 1 | 4 | 4 |
Inspection: N/A






















Saturday, June 13, 2026
Clear, 77°F
TDI hanging drywall at the garage conversion.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| TDI | 2 | 8 | 16 |
Inspection: N/A