All updates
Week 24 of 34

Week of June 01 — June 05, 2026

5 days on site. 76 photos. Electric, Inspection, Plumbing, Roofing, Stucco, Tile.

June 1, 2026June 5, 20265 days76 photos
ElectricInspectionPlumbingRoofingStuccoTile

Monday, June 01, 2026

Partially cloudy, 71°F

ACCI installing roofing at Garage Conversion. Metal Flashing at Existing Duplex/Garage Interface in production.

Insulation Labs installing insulation at Garage Conversion.

ZSP preparing garage and laundry area washer boxes for plumbing inspection tomorrow 6/2. Lines under pressure.

Marq Plastering moving sand out of side walk and tarping scaffolding to prepare for scratch and brown.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
ACCI3824
ZSP2816
Marq248

Inspection: N/A


IMG_2238.jpeg

IMG_2239.jpeg

IMG_2236.jpeg

IMG_2237.jpeg

IMG_2232.jpeg

IMG_2234.jpeg

IMG_2229.jpeg

IMG_2230.jpeg

IMG_2226.jpeg

IMG_2228.jpeg

IMG_2221.jpeg

IMG_2222.jpeg

IMG_2219.jpeg

IMG_2220.jpeg

IMG_2217.jpeg

IMG_2218.jpeg

IMG_2215.jpeg

IMG_2216.jpeg


Tuesday, June 02, 2026

Clear, 68°F

Coastal on site, laying out tile for bathroom in B1, C1, C2. All tile delivered to site.

Marq shooting cement at B and C.

ZSP (Adrian) prepping for inspection and centering shower valves/head.

JBG finished shearing and furring out walls after inspection.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Marq9872
Coastal2816
ZSPJBG124448

Inspection: Jim, city inspector (619-990-3772) on site at 10:00 AM to inspect garage MEP rough-in and insulation. Passed both. Only comment was to reverse direction of the bathroom fart fan and exhaust towards the parking area. Exhaust fans must have clearance from operable windows.

AC Electric fixed fan orientation.


IMG_2310.jpeg

IMG_2309.jpeg

IMG_2307.jpeg

IMG_2308.jpeg

IMG_2305.jpeg

IMG_2306.jpeg

IMG_2302.jpeg

IMG_2303.jpeg

IMG_2299.jpeg

IMG_2301.jpeg

IMG_2294.jpeg

IMG_2296.jpeg

IMG_2292.jpeg

IMG_2293.jpeg

IMG_2282.jpeg

IMG_2283.jpeg

IMG_2280.jpeg

IMG_2281.jpeg

IMG_2278.jpeg

IMG_2279.jpeg

IMG_2275.jpeg

IMG_2277.jpeg

IMG_2271.jpeg

IMG_2274.jpeg

IMG_2266.jpeg

IMG_2270.jpeg


Wednesday, June 03, 2026

Clear, 69°F

Coastal installing wall tile at B1 and C1 showers. Targeting 6/5 completion date for first floor showers.

Nick (Clear HVAC) on site to confirm what material is needed to complete garage conversion ducting.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Coastal2816

Inspection: N/A


IMG_2341.jpeg

IMG_2340.jpeg

IMG_2347.jpeg

IMG_2369.jpeg

IMG_2371.jpeg


Thursday, June 04, 2026

Clear, 71°F

Coastal continuing to install tile at B1 and C1 showers.

AC Electric wiring in missed under cabinet lights. TDI to mud and sand patches when drywall at garage is installed.

Marq powerwashing and masking to prepare for colorcoat.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Coastal2816
AC Electric144
Marq2816

Inspection: N/A


1000010286.jpeg

80229536262__B3782E86-6B1D-4093-B621-16B5D4B15898.jpeg

IMG_2860.jpeg

80229723454__C8E451F6-372E-444A-87E7-D15F614CEEC0.jpeg

80229722461__529CEBF7-DD3A-4591-8B05-E0430B96DC8E.jpeg

80229716955__714705C5-36FE-4052-993F-6151973B8792.jpeg


Friday, June 05, 2026

Overcast, 64°F

Marq picking up quality control patching and preparing for color coat.

Coastal finishing wall tile at B1/C1. Grouting on saturday. Discussed floor tile layout with Paige. Decided to do whatever required less cuts and would be the most waterproof.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Coastal2816
Marq188

Inspection: N/A


IMG_2479.jpeg

IMG_2481.jpeg

IMG_2480.jpeg

IMG_2482.jpeg

IMG_2483.jpeg

IMG_2488.jpeg

IMG_2487.jpeg

IMG_2490.jpeg

IMG_2489.jpeg

IMG_2492.jpeg

IMG_2491.jpeg

IMG_2497.jpeg

IMG_2493.jpeg

IMG_2495.jpeg

IMG_2496.jpeg

IMG_2498.jpeg

IMG_2494.jpeg

IMG_2500.jpeg

IMG_2499.jpeg

IMG_2502.jpeg

IMG_2501.jpeg