Week 23 of 34

Week of May 26 — May 29, 2026

4 days on site. 56 photos. Electric, Framing, HVAC, Inspection, Plumbing, Stucco, Tile, Traffic Coating.

May 26, 2026May 29, 20264 days56 photos
ElectricFramingHVACInspectionPlumbingStuccoTileTraffic Coating

Tuesday, May 26, 2026

Overcast, 65°F

JB General on site, installing shear and interior walls at garage conversion.

Rete's finishing waterproofing repair at stairs.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General2816
Rete's2816

Inspection: Dave Finney on site at 11 am for shear/roof inspection at garage conversion. Passed


IMG_1899.jpeg

IMG_1898.jpeg

IMG_1897.jpeg

IMG_1903.jpeg

IMG_1900.jpeg

IMG_1915.jpeg

IMG_1905.jpeg

IMG_1912.jpeg

IMG_1911.jpeg

IMG_1917.jpeg

IMG_1914.jpeg

IMG_1919.jpeg

IMG_1918.jpeg


Wednesday, May 27, 2026

Overcast, 64°F

Marq installing continuous vents, paper and lath. Preparing for inspection on 5/28.

AC Electric finishing rough-in at Garage Conversion. Preparing for inspection on 5/28.

Coastal finishing Unit B1 shower water proofing and filling pans with water for inspection on 5/28.

Zack Smith on site to look at layout.

TDI on site to clean up concrete floors.

Max from ACCI on site to discuss flashing detail between garage and existing duplex roofs.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
AC Electric248
Marq3824
Coastal188

Inspection: N/A


IMG_1932.jpeg

IMG_1931.jpeg

IMG_1936.jpeg

IMG_1930.jpeg

IMG_1943.jpeg

IMG_1934.jpeg

IMG_1947.jpeg

IMG_1946.jpeg

IMG_1952.jpeg

IMG_1951.jpeg

IMG_1956.jpeg

IMG_1954.jpeg

IMG_1958.jpeg

IMG_1957.jpeg

IMG_1960.jpeg

IMG_1959.jpeg


Thursday, May 28, 2026

Partially cloudy, 68°F

Marq finishing paper and lath at buildings B and C and cleaning up site. Materials expected at 8 AM on 5/29.

AC Electric finished wiring at Garage Conversion.

Clear HVAC installing mini-split at garage conversion.

JB General installing shower wing wall and 1x at roof fascia.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Marq3824
AC Electric144
JB General111
Clear HVAC144

Inspection: Dave Finney on site at 1 PM. Passed electrical rough-in at garage conversion. Passed paper and lath and shower waterproofing at Buildings B and C.


IMG_2016.jpeg

IMG_2017.jpeg

IMG_2014.jpeg

IMG_2015.jpeg

IMG_2012.jpeg

IMG_2013.jpeg

IMG_2010.jpeg

IMG_2011.jpeg

IMG_2008.jpeg

IMG_2009.jpeg

IMG_2006.jpeg

IMG_2007.jpeg

IMG_1992.jpeg

IMG_1993.jpeg

IMG_1990.jpeg

IMG_1991.jpeg

IMG_1988.jpeg

IMG_1989.jpeg


Friday, May 29, 2026

Partially cloudy, 62°F

ZSP roughing in at garage conversion.

Stucco materials delivered at 9:30 AM.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
ZSP2816

Inspection: N/A


IMG_2051.jpeg

IMG_2053.jpeg

IMG_2054.jpeg

IMG_2059.jpeg

IMG_2060.jpeg

IMG_2057.jpeg

IMG_2058.jpeg

IMG_2086.jpeg

IMG_2087.jpeg