Week 22 of 34

Week of May 18 — May 22, 2026

5 days on site. 65 photos. DFH, Demolition, Drywall, Electric, Framing, Insulation, Tile, Traffic Coating.

May 18, 2026May 22, 20265 days65 photos
DFHDemolitionDrywallElectricFramingInsulationTileTraffic Coating

Monday, May 18, 2026

Partially cloudy, 67°F

JB General fixing stair framing. Demo of garage wall and roof complete. Garage framing in progress.

AC Electric installing ATT weather head.

TDI finishing soffit at Building C and sanding.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
AC Electric248
JB General4832

Inspection: N/A


IMG_1511.jpeg

IMG_1513.jpeg

IMG_1512.jpeg

IMG_1518.jpeg

IMG_1517.jpeg

IMG_1520.jpeg

IMG_1519.jpeg

IMG_6805.jpeg

DEBE7537-8DA1-4D04-BD27-C7D81608F282.jpeg

IMG_6807.jpeg

IMG_6806.jpeg


Tuesday, May 19, 2026

Partially cloudy, 72°F

Garage framing in progress. Curb chipped out and new wall erected. Stair repair complete.

TDI finishing sanding and cleaning up site.

Insulation Labs insulating existing duplex wall.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General6848
TDI188
Insulation Labs224

Inspection: N/A


IMG_1562.jpeg

IMG_1563.jpeg

IMG_1560.jpeg

IMG_1561.jpeg

IMG_1558.jpeg

IMG_1559.jpeg

IMG_1556.jpeg

IMG_1557.jpeg

IMG_1554.jpeg

IMG_1555.jpeg

IMG_1552.jpeg

IMG_1553.jpeg

IMG_1550.jpeg

IMG_1551.jpeg

IMG_1548.jpeg

IMG_1549.jpeg

IMG_1547.jpeg


Wednesday, May 20, 2026

Clear, 72°F

Stair correction completed. Ready for waterproofing.

Existing duplex wall at garage conversion interface completed. Interior walls erected. Joists being ripped and prepped for installation. Curb at new entry door being chipped out.

Shower waterproofing in progress.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General4.5836
Coastal188

Inspection: N/A


IMG_1610.jpeg

IMG_1604.jpeg

IMG_1603.jpeg

IMG_1606.jpeg

IMG_1605.jpeg

IMG_1609.jpeg

IMG_1607.jpeg

2782.jpeg

2783.jpeg

2780.jpeg

2781.jpeg

2778.jpeg

2779.jpeg

2776.jpeg

2777.jpeg

1000016824.jpeg

2775.jpeg


Thursday, May 21, 2026

Clear, 68°F

JB General working on garage conversion. Redguarding seismic gaps between garage and existing duplex. Joists installed and roof sheathing started. Blocking of exterior walls completed.

Coastal waterproofing showers.

Rete's patching traffic coating at stairs.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General6848
Coastal2816
Rete's3515

Inspection: N/A


IMG_1682.jpeg

IMG_1683.jpeg

IMG_1714.jpeg

IMG_1691.jpeg

IMG_1716.jpeg

IMG_1720.jpeg

IMG_1722.jpeg

IMG_1721.jpeg

IMG_1727.jpeg

IMG_1725.jpeg

2790.jpeg

2789.jpeg


Friday, May 22, 2026

Clear, 69°F

JB General blocking garage walls, installing roof sheathing, and cutting back existing duplex wing wall.

Taylor Trim installing exterior doors at B and C and closet shelf and pole.

TDI fixing soffit in Building B 1 shower. Coastal waterproofing walls.

Rete's working on stair repairs.

ML picked up job site.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General6848
Taylor Trim2816
Rete's2816
Coastal188

Inspection: N/A


IMG_1755.jpeg

![IMG_1754 - 1.jpeg](/photos/2026-05-22/IMG_1754 - 1.jpeg)

IMG_1758.jpeg

![IMG_1757 - 1.jpeg](/photos/2026-05-22/IMG_1757 - 1.jpeg)

![IMG_1763 - 1.jpeg](/photos/2026-05-22/IMG_1763 - 1.jpeg)

![IMG_1762 - 1.jpeg](/photos/2026-05-22/IMG_1762 - 1.jpeg)

![IMG_1759 - 1.jpeg](/photos/2026-05-22/IMG_1759 - 1.jpeg)

![IMG_1764 - 1.jpeg](/photos/2026-05-22/IMG_1764 - 1.jpeg)