All updates
Week 20 of 34

Week of May 04 — May 08, 2026

5 days on site. 78 photos. DFH, Delay, Drywall, Electric, Framing, HVAC, Inspection, Insulation, Plumbing, ROW, Roofing, Solar, Stucco.

May 4, 2026May 8, 20265 days78 photos
DFHDelayDrywallElectricFramingHVACInspectionInsulationPlumbingROWRoofingSolarStucco

Monday, May 04, 2026

Partially cloudy, 62°F

Insulation Labs on site, insulating Structure B and spraying foam around openings.

JB General added backing for future grab handles in bathrooms

Gold Coast (C3 Civil) doing final pave).


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Insulation Labs2816
C3 Civil4416
JB General122

Inspection: N/A


IMG_0913.jpeg

IMG_0904.jpeg

IMG_0916.jpeg

IMG_0915.jpeg

IMG_0914.jpeg

IMG_0917.jpeg

IMG_0919.jpeg

IMG_0918.jpeg

IMG_0920.jpeg

IMG_0925.jpeg

IMG_0922.jpeg

IMG_0921.jpeg

IMG_0923.jpeg

IMG_0924.jpeg

IMG_0927.jpeg

IMG_0926.jpeg

IMG_0931.jpeg


Tuesday, May 05, 2026

Partially cloudy, 64°F

Insulation labs on site, finishing building B. Slight rain in the morning, but insulation was not affected.

Traditions Drywall on site to prep for stocking and installation on Friday. Minor comments on Electrical and Plumbing Rough-in.

Scott from Primera on site to double check. Asked us to move water box to create more space between the sink and range in Building B units.

AC Electric on site, picking up minor changes and meeting with inspector for meter inspection. AC Electric met with ATT at 8 AM to discuss weatherhead location. ML to schedule meeting with ATT, SDGE and AC Electric.

ZSP on site, capping gas and removing lines from garage roof.

Rigid Insulation for Marq plastering delivered to site.

Taylor Trim installing remaining pocket door frames and strorage room door frame.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Insulation Labs2816
ZSP144
AC Electric144
Taylor Trim166

Inspection: Dave Finney and Lee Weske on site at 2PM for Meter Inspection. Inspectors asked us to label meters, move fence stands off sidewalk, and improve BMPs.

ML to add silt fence this week. Fence corrected. AC Electric to add labels after DF confirms addressing.


IMG_0960.jpeg

IMG_0959.jpeg

IMG_0958.jpeg

IMG_0966.jpeg

IMG_0961.jpeg

IMG_0976.jpeg

IMG_0975.jpeg

IMG_0978.jpeg

IMG_0977.jpeg

IMG_0980.jpeg

IMG_0979.jpeg

IMG_0981.jpeg

IMG_0982.jpeg

IMG_0985.jpeg

IMG_0983.jpeg

IMG_0987.jpeg

IMG_0986.jpeg

IMG_0989.jpeg

IMG_0988.jpeg

IMG_0993.jpeg

IMG_0991.jpeg

IMG_0992.jpeg

IMG_0990.jpeg


Wednesday, May 06, 2026

Clear, 68°F

Sergio, TDI, on site to straight edge walls and ceilings and confirm soffit layout, and electrical rough-in.

JB General on site, shimming to prepare for drywall. Adjusting one door header in Building C, Unit 1. Jeremy on site to do site concrete take-offs.

AC Electric tweaking fixture heights on first floor units.

Fernando from Taylor Trim on site to measure interior door rough openings and prepare to order.

ML picking up trash around site.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General2612
AC Electric144

Inspection: Dave Finney on site at 11 AM for insulation inspection at Building B and C. Passed!


IMG_1014.jpeg

IMG_1021.jpeg

IMG_1019.jpeg

IMG_1015.jpeg


Thursday, May 07, 2026

Partially cloudy, 68°F

JB General making small adjustments for stucco crew. Niches added in C2 and B1. Overhang hung on building C.

Marq on site wrapping Building B and C in Tyvek. ML and Ivan walked sure and reviewed weep screed heights.

ZSP working on garage conversion underground.

Clear HVAC pressure testing equipment.

Response to RFI 007 received. See attached.

Senior Inspector, Lee, called and let us know that we would be sent a correction notice to submit electrical plans for review. This is a new requirement that the city is unrolling for projects with 3+ meters. 1070 looped in. See attached.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
Clear HVAC188
JB General188
ZSP188
Marq2816

Inspection: N/A


IMG_1045.jpeg

IMG_1077.jpeg

IMG_1048.jpeg

IMG_1044.jpeg

IMG_1051.jpeg

IMG_1049.jpeg

IMG_1089.jpeg

IMG_1050.jpeg

IMG_1092.jpeg

IMG_1090.jpeg

IMG_1098.jpeg

IMG_1095.jpeg

IMG_1101.jpeg

IMG_1099.jpeg

![Correction Notice to submit Electrical plans.pdf](/photos/2026-05-07/Correction Notice to submit Electrical plans.pdf)

![1070_RFI 007-Roofing _Response 05.07.2026.pdf](/photos/2026-05-07/1070_RFI 007-Roofing _Response 05.07.2026.pdf)


Friday, May 08, 2026

Overcast, 65°F

Zack Smith finishing Garage Conversion underground Plumbing.

ACCI cutting back rafter where existing duplex roof intersects with garage conversion. Area wrapped in plastic for temporary water prevention. Also applying roofing to overhang at building C.

Clear HVAC installing microwave vent penetrations and flashing.

TDI handloading material into units.

Marq plastering continuing to install weep screed and paper at B and C.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
ACCI2816
Traditions Drywall6848
ZSP188
Clear HVAC122
Marq236

Inspection: N/A


Delay: Sauder is changing their manufacturing process for slab style doors. Delivery window increased from 6 weeks to 7-8 weeks.

![3312 Luna - Landscaping Plans - R1.pdf](/photos/2026-05-08/3312 Luna - Landscaping Plans - R1.pdf)

IMG_1131.jpeg

IMG_1136.jpeg

IMG_1133.jpeg

IMG_1142.jpeg

IMG_1140.jpeg

IMG_1145.jpeg

IMG_1143.jpeg

IMG_1149.jpeg

IMG_1146.jpeg

IMG_1147.jpeg

IMG_1148.jpeg

IMG_1152.jpeg

IMG_1151.jpeg

IMG_1155.jpeg

IMG_1153.jpeg

IMG_1156.jpeg

IMG_1157.jpeg