Week 19 of 34

Week of April 27 — May 01, 2026

4 days on site. 54 photos. DFH, Electric, Framing, HVAC, Inspection, Plumbing, Roofing, Scaffolding, Traffic Coating.

April 27, 2026May 1, 20264 days54 photos
DFHElectricFramingHVACInspectionPlumbingRoofingScaffoldingTraffic Coating

Monday, April 27, 2026

Partially cloudy, 64°F

Rete's on site, sloping stair landings at Building C and prepping for traffic coating installation.

AC Electric on site, finishing Building C.

ZSP on site working on water connection to Building B.

Remaining scaffolding being erected.

JB General on site doing clean up, hardware pickup and blocking at Buildings B and C.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General4832
ZSP2816
AC Electric3825
Rete's3824

Inspection: Danny on site at 3:00 PM to inspect Building B roof nailing and shear. Passed.


IMG_0613.jpeg

IMG_0612.jpeg

IMG_0616.jpeg

IMG_0614.jpeg

IMG_0618.jpeg

IMG_0617.jpeg

IMG_0637.jpeg

IMG_0636.jpeg

IMG_0639.jpeg

IMG_0638.jpeg


Tuesday, April 28, 2026

Clear, 65°F

ACCI on site, installing 1.5" rigid insulation and OSB.

Rete's continuing to lath stairs at Building B. Pouring cementious material to slope stair landings at Building C.

JB General contuninuing hardware pick-ups and blocking at Building B. Pony walls for penninsulas going in at Building C. Garage layout in progress. Informal RFI submitted to 1070 regarding existing conditions. See attachment.

Zack Smith Plumbing and AC Electric continuing rough-in at B and C. ZSP starting layout at D.

General site clean up and trash haul off in progress.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
ACCI4832
Rete's3824
ZSP4832
JB General5840
AC Electric2816

Inspection: N/A


![GARAGE CONVERSION STRUCTURAL ISSUES.pdf](/photos/2026-04-28/GARAGE CONVERSION STRUCTURAL ISSUES.pdf)

IMG_0650.jpeg

IMG_0662.jpeg

IMG_0671.jpeg

IMG_0663.jpeg

IMG_0673.jpeg

IMG_0672.jpeg

IMG_0675.jpeg

IMG_0674.jpeg

IMG_0677.jpeg

IMG_0676.jpeg

IMG_0681.jpeg

IMG_0678.jpeg


Thursday, April 30, 2026

Partially cloudy, 68°F

Zack Smith Plumbing and AC Electric prepping for inspection.

Taylor Trim installing remaining exterior door frames and pocket door frames.

Clear HVAC installing second floor units at Building B.

ACCI installing GAF Liberty SBS Self-Adhering Roofing System and bonderized drip edge.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
AC Electric2816
ZSP3824
ACCI4832
Clear HVAC4832

Inspection: N/A


Delay: Work on garage paused until RFI repsonse received.

IMG_0746.jpeg

IMG_0751.jpeg

IMG_0749.jpeg

IMG_0753.jpeg

IMG_0752.jpeg

IMG_0755.jpeg

IMG_0754.jpeg

IMG_0757.jpeg

IMG_0756.jpeg

IMG_0760.jpeg

IMG_0758.jpeg


Friday, May 01, 2026

Clear, 70°F

ACCI on site, finishing roofing at Structure B and C.

Clear HVAC installing ducts for fart fans.

ZSP filling lines and checking for leaks.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
ACCI4832
ZSP3412
Clear HVAC2816

Inspection: Dave Finney on site at 11:30 AM to complete Building B shear wall inspecing for Wall Type 1, and MEP Rough-in. Asked for bushings at subpanels at metal openingings and addtional nail plates and plumbing penetrations. Passed both B and C.


IMG_0812.jpeg

IMG_0813.jpeg

IMG_0808.jpeg

IMG_0809.jpeg

IMG_0804.jpeg

IMG_0805.jpeg

IMG_0802.jpeg

IMG_0803.jpeg

IMG_0800.jpeg

IMG_0801.jpeg

IMG_0798.jpeg

IMG_0799.jpeg

IMG_0789.jpeg

IMG_0797.jpeg

IMG_0794.jpeg

IMG_0788.jpeg

IMG_0795.jpeg

IMG_0791.jpeg

IMG_0793.jpeg

IMG_0792.jpeg