Week 17 of 34

Week of April 13 — April 17, 2026

5 days on site. 57 photos. Electric, Foundations, Framing.

April 13, 2026April 17, 20265 days57 photos
ElectricFoundationsFraming

Monday, April 13, 2026

Partially cloudy, 65°F

JB General on site, working on second floor framing. Building B stair templating in progress.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General5840

Inspection: N/A



Tuesday, April 14, 2026

Clear, 69°F

JB General continuing stair framing and second floor walls. Hand loading material to second floor. Joists to start tomorrow afternoon or Thursday morning. Stairs expected to be complete by Friday.

Building C stair slab being poured.

Jeremy and Javier from AC electric walked site to discuss electrical layout with Morgan. AC Electric digging to prep for running wires tomorrow.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General10880
AC Electric2816

Inspection: N/A


2693.jpeg

2694.jpeg

2695.jpeg

2691.jpeg

2692.jpeg

2689.jpeg

2690.jpeg

IMG_0071.jpeg

IMG_0074.jpeg

IMG_0067.jpeg

IMG_0070.jpeg

IMG_0065.jpeg

IMG_0066.jpeg

IMG_0063.jpeg

IMG_0064.jpeg

IMG_0061.jpeg

IMG_0062.jpeg

IMG_0057.jpeg

IMG_0058.jpeg

IMG_0054.jpeg

IMG_0056.jpeg


Wednesday, April 15, 2026

Clear, 70°F

JB General on site. Building B stairs installed. Building C stairs in progress. All exterior walls for Building B erected and braced. Interior walls in progress.

Sawcutting slab at garage for new footings and plumbing trenches.

AC electric on site, wrapping up first floor layout and installing boxes. Prepping to run wire.

Clear HVAC (Reuven and Javier) on site for site walk to discuss HVAC layout. See attached exhibit.

Dennis from Window Solutions on site to measure rough openings. Windows expected to be delivered on 4/20/26.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General7856
AC Electric3824

Inspection: N/A


![3312 LUNA - B + C HVAC LAYOUTS.pdf](/photos/2026-04-15/3312 LUNA - B + C HVAC LAYOUTS.pdf)

IMG_0106.jpeg

IMG_0111.jpeg

IMG_0107.jpeg

IMG_0109.jpeg

IMG_0110.jpeg

IMG_0113.jpeg

IMG_0112.jpeg

IMG_0115.jpeg

IMG_0114.jpeg

IMG_0118.jpeg

IMG_0116.jpeg

IMG_0130.jpeg

IMG_0128.jpeg


Thursday, April 16, 2026

Partially cloudy, 68°F

Exterior walls at Building B and C complete. Interior walls in progress. Stairs at Building C in progress.

Trenches at garage conversion dug and ready for rebar.

Per owner approval, WH1 relocated to laundry area. WH1 will service Structure D and laundry area. Electricians to connect to house panel.

Electrical rough-in in progress at first floor of both buildings.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General7856
AC Electric3824

Inspection: N/A


![Screenshot 2026-04-16 123505.png](/photos/2026-04-16/Screenshot 2026-04-16 123505.png)

IMG_0154.jpeg

IMG_0151.jpeg

IMG_0156.jpeg

IMG_0155.jpeg

IMG_0158.jpeg

IMG_0157.jpeg

IMG_0162.jpeg

IMG_0161.jpeg

IMG_0163.png

IMG_0164.png


Friday, April 17, 2026

Clear, 71°F

JB General on site working on Building C stairs and finishing Building B interior walls. Starting joist layout on Building C.

Taylor Trim measuring ROs to prep for exterior frames installation next week.

AC Electric wiring in first floor at both buildings.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General6848
AC Electric3824

Inspection: N/A