Week 15 of 34

Week of March 30 — April 03, 2026

4 days on site. 34 photos. Electric, Foundations, Framing, Inspection.

March 30, 2026April 3, 20264 days34 photos
ElectricFoundationsFramingInspection

Monday, March 30, 2026

Partially cloudy, 73°F

AC Electric installing switch gear, rigid riser and grounding rod at existing house.

JB General completed floor joists at Structure C and started joists at Structure B.

Inspection of sticks/hold downs scheduled for Wednesday. Floor sheathing to start tomorrow.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General5840
AC Electric3824

Inspection: N/A


IMG_9459.jpeg

IMG_9463.jpeg

IMG_9461.jpeg

IMG_9465.jpeg

IMG_9464.jpeg

IMG_9467.jpeg

IMG_9466.jpeg

IMG_9469.jpeg

IMG_9468.jpeg

IMG_9490.jpeg

IMG_9488.jpeg


Wednesday, April 01, 2026

Partially cloudy, 65°F

JB General finishing floor joists at Structure B.

Dave Finney came for inspection and gave a partial pass for sticks and holddowns.

JB General to proceed with Sheathing.

Scaffolding scheduled for Monday. AC Electric to start rough-in on Friday.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General5840

Inspection: Partial framing inspection for Buildings B and C.


Delay: Pending answer to RFI006, regarding plumbing penetration. 1070 says it will take a week to get a response, pushing back plumbing rough-in.

2661.jpeg

2662.jpeg

2664.jpeg

2663.jpeg


Thursday, April 02, 2026

Overcast, 67°F

JB General on site, working on sheathing and foundation drains.

Prepping for scaffolding install and MEP rough-in next week.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General5840

Inspection: N/A


IMG_9601.jpeg

IMG_9600.jpeg

IMG_9603.jpeg

IMG_9602.jpeg

IMG_9606.jpeg

IMG_9604.jpeg

IMG_9609.jpeg

IMG_9608.jpeg

IMG_9611.jpeg

IMG_9610.jpeg


Friday, April 03, 2026

Partially cloudy, 69°F

JB General continuing to sheath both buildings. Drainage mats and drains installed along back property line and walls backfilled to prepare for scaffolding installation.

First floor scaffolding to be installed tomorrow (4/3/26).


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General5840

Inspection: N/A


IMG_9636.jpeg

IMG_9635.jpeg

IMG_9634.jpeg

IMG_9638.jpeg

IMG_9637.jpeg

IMG_9640.jpeg

IMG_9639.jpeg

IMG_9642.jpeg

IMG_9641.jpeg