Week 14 of 34

Week of March 23 — March 27, 2026

5 days on site. 51 photos. Foundations, Framing, ROW.

March 23, 2026March 27, 20265 days51 photos
FoundationsFramingROW

Monday, March 23, 2026

Clear, 72°F

JB General on site. Walls for Structure C stair landing formed and templated. Footings for Structure B Stairs and WH enclosure hand dug. First floor framing still in progress.

C3, continuing to dig trench for new water service. Base pave complete.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
C34832
JB General9872

Inspection: N/A


IMG_9220.jpeg

IMG_9222.jpeg

IMG_9218.jpeg

IMG_9219.jpeg

IMG_9214.jpeg

IMG_9217.jpeg

IMG_9204.jpeg

IMG_9211.jpeg

IMG_9201.jpeg

IMG_9202.jpeg

IMG_9197.jpeg

IMG_9198.jpeg


Tuesday, March 24, 2026

Clear, 74°F

JB General added rebar and forms for Structure B stair footing.

Debris from fence demo, scrap pieces of wood, and other trash hauled off. More lumber delivered.

First floor framing still in progress. Layout for Structure B interior walls completed.

C3 connected new water meter on-site plumbing. Will return in 30 days to pave and replace sidewalk panel.

Dennis Hartley (Window Solutions) on site to measure and verify first floor window openings.

KTC pending detail from 1070 for pocket doors. Pricing for 8'-0" bi-pass doors received. Closet slider will change to full height to create more storage for tenants.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
C3248
JB General8864

Inspection: N/A


IMG_9255.jpeg

IMG_9252.jpeg

IMG_9254.jpeg

IMG_9250.jpeg

IMG_9251.jpeg

IMG_9248.jpeg

IMG_9249.jpeg

IMG_9246.jpeg

IMG_9247.jpeg

IMG_9238.jpeg

IMG_9245.jpeg


Wednesday, March 25, 2026

Clear, 75°F

JB General on site, framing first floor walls. Starting fire blocking.

Taylor Trim stopped by to take progress pictures.

Concrete scheduled for 10 AM tomorrow for stair footings.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General4832
JB General144

Inspection: Dave Finney passed stair footings. On site from 11:55 AM to 12:05 AM.


IMG_9272.jpeg

IMG_9277.jpeg

IMG_9273.jpeg

IMG_9276.jpeg

IMG_9278.jpeg


Thursday, March 26, 2026

Clear, 64°F

JB General continuing first floor framing. Top plates on Building B completed. Blocking in progress. Will start setting joists tomorrow.

Stair footing at Building B and walls at Building C poured at 10:30 AM.

Zack Smith on site to check on progress.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General4832
JB General224

Inspection: N/A


IMG_9369.jpeg

IMG_9362.jpeg

IMG_9363.jpeg

IMG_9359.jpeg

IMG_9360.jpeg

IMG_9354.jpeg

IMG_9358.jpeg

IMG_9335.jpeg

IMG_9351.jpeg

IMG_9339.jpeg

IMG_9344.jpeg


Friday, March 27, 2026

Clear, 76°F

Concrete from yesterday's pour stripped.

All blocking installed on exterior walls. Installation of joists on Building C in progress.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS
JB General5840

Inspection: N/A


IMG_9387.jpeg

IMG_9385.jpeg

IMG_9384.jpeg

IMG_9388.jpeg

IMG_9386.jpeg

IMG_9390.jpeg

IMG_9389.jpeg

IMG_9392.jpeg

IMG_9391.jpeg

IMG_9393.jpeg

IMG_9394.jpeg

2647.jpeg