Week of February 23 — February 27, 2026
5 days on site. 16 photos. Earthwork, Foundations.
Monday, February 23, 2026
Partially cloudy, 62°F
JB General on site digging foundations for Structure B.
Site still slightly wet.
Foundation closest to existing building will need to be formed to prevent electrical conduit from being within the footing.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JB General | 4 | 8 | 32 |
Inspection: N/A




Tuesday, February 24, 2026
Partially cloudy, 60°F
JB General on site, digging foundations for Structure B.
Site still slightly wet.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JB General | 4 | 8 | 32 |
Inspection: Jason from Fenagh on site at 8:30 AM. Requested footings in some areas be dug 6” deeper and some soft areas be compacted more. Re-inspection scheduled for 9 AM tomorrow.





Wednesday, February 25, 2026
Clear, 75°F
JB General on site, digging footings. Fenagh was on site at at 9 AM and passed bottom of footing and recompaction. Some of the previously run plumbing needed to be relocated out of the footing.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JB General | 5 | 8 | 40 |
| ZSP | 2 | 2 | 4 |
Inspection: Fenagh on site at 9 AM to inspect bottom of footings for Structure B.



Thursday, February 26, 2026
Clear, 75°F
JB General on site, setting rebar and forming footings for Building B.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JB General | 4 | 8 | 32 |
Inspection: ---
Friday, February 27, 2026
Clear, 84°F
JB General preparing for inspection Monday. Templating, forming, setting bar and playing rebar caps.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JB General | 4 | 2 | 8 |
| JB General | 2 | 2 | 4 |
Inspection: N/A