All updates
Week 9 of 34
Week of February 17 — February 20, 2026
2 days on site. 9 photos. Delay, SDGE.
February 17, 2026 — February 20, 20262 days9 photos
DelaySDGE
Tuesday, February 17, 2026
Partially cloudy, 59°F
Heavy rains on Monday (2/16) have delayed work. More rain expected Wednesday and Thursday.
ML on site to clean sidewalk, adjust BMPs and retarp spoils, stockpiled on building C.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
Inspection: N/A
Delay: Rain delay. No work expected until 2/23, best case scenario.





Friday, February 20, 2026
Clear, 51°F
Site still wet and muddy. No work being done.
SDGE on site to install new temporary power but could not without access to the neighbors’ property. ML working with Diamond to contact the neighbor and reschedule.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
Inspection: N/A
Delay: Rain delay.