2 days on site. 9 photos. Delay, SDGE.

February 17, 2026February 20, 20262 days9 photos
DelaySDGE

Tuesday, February 17, 2026

Partially cloudy, 59°F

Heavy rains on Monday (2/16) have delayed work. More rain expected Wednesday and Thursday.

ML on site to clean sidewalk, adjust BMPs and retarp spoils, stockpiled on building C.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS

Inspection: N/A


Delay: Rain delay. No work expected until 2/23, best case scenario.

IMG_8212.jpeg

IMG_8211.jpeg

IMG_8208.jpeg

IMG_8216.jpeg

IMG_8213.jpeg


Friday, February 20, 2026

Clear, 51°F

Site still wet and muddy. No work being done.

SDGE on site to install new temporary power but could not without access to the neighbors’ property. ML working with Diamond to contact the neighbor and reschedule.


Manpower:

SUBCONTRACTORWORKERSHOURS WORKEDTOTAL HOURS

Inspection: N/A


Delay: Rain delay.