Week of August 24 — August 26, 2026
3 days on site. 27 photos. Appliances, Electric, HVAC, Landscape, Plumbing, SDGE, Solar.
Monday, August 24, 2026
Partially cloudy, 85°F
JBG templating railing at Structure Site concrete and continuing to reinstall turf and fence at front of property.
AC Electric installing NEMA boxes for ATT.
ZSP cleaning up remaining materials.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| JBG | 2 | 4 | 8 |
| AC Electric | 1 | 2 | 2 |
| ZSP | 1 | 2 | 2 |
Inspection: N/A
Delay: Pending temp power removal and permanent power install.





Tuesday, August 25, 2026
Clear, 79°F
JBG finishing turf replacement and cleaning up site.
SDGE contractors on site at 10:30 AM to install permanent power.
AC Electric on site for energization. Initial checks of lights, smoke detectors, etc... completed.
Clear finishing microwave ducting.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| AC Electric | 2 | 3 | 6 |
| Clear | 1 | 8 | 8 |
| JBG | 3 | 3 | 9 |
Inspection: N/A








Wednesday, August 26, 2026
Partially cloudy, 85°F
ZSP testing all 7 water heaters and fixtures in the new units. Sunline hit the hold water line going from the water heater to 3312, and ZSP repaired.
Lowe's sent someone to install anti-tip brackets on the ranges in B&C. One anti-strain clip was missing. Lowe's to provide and send installer back.
ML checked all dishwashers, microwaves and garage conversion fridge.
Sunline on site, continuing install. ML was told they were having issues commissioning and would need to reach out to Enphase.
Clear continuning to install rigid ducting on microwave hoods and check split units.
Manpower:
| SUBCONTRACTOR | WORKERS | HOURS WORKED | TOTAL HOURS |
|---|---|---|---|
| ZSP | 1 | 8 | 8 |
| Clear | 1 | 8 | 8 |
Inspection: N/A
Delay: Pending installation of Fridges by Costco and missing range cord from Ikea. Sunline is aiming for solar inspection next week.