Chapter 8The Contract

Negotiating a $1.37M Construction Contract

How the contract works, what value engineering means, and why we split the savings 65/35

January 13, 20263 min read
constructionGCcontractvalue-engineering

Finding Koala-T Construction

After talking to several general contractors, I picked Koala-T Construction. Morgan Lyew leads their preconstruction team. He stood out for three reasons: detailed budgets, clear communication, and experience building multiple ADUs in San Diego.

How the Contract Works

We signed a Cost Plus Fee with Guaranteed Maximum Price (GMP) contract on January 13, 2026. Let me explain what that means in plain English.

Cost Plus Fee means I pay the actual cost of materials and labor, plus a fee to the contractor. I see every receipt.

Guaranteed Maximum Price means there's a cap. No matter what happens, I won't pay more than the agreed maximum.

Contract DetailAmount
Maximum price (GMP)$1,367,346
Contractor fee5% ($65,112)
Construction time30 weeks (~8 months)
Savings split65% to me / 35% to contractor

That savings split is important. If the project costs less than the maximum, we share the leftover money. That gives the contractor a reason to save money without cutting corners.

Cutting $94K Through Value Engineering

Before we signed, we worked together to cut $94,000 from the budget. This is called value engineering -- finding ways to spend less without hurting quality.

Some examples:

  • Simpler landscaping that still looks good
  • Swapping materials for cheaper ones that work just as well
  • Smarter framing design
  • Buying some appliances ourselves instead of through the contractor

This wasn't a fight. Morgan suggested options for each item. We talked about trade-offs. We agreed on cuts that saved money without making the homes worse.

Where the Money Goes

CategoryCost% of Total
Site supervision$172,94012.6%
Wood framing$169,91612.4%
Electrical$118,8508.7%
Concrete foundations$118,0408.6%
Landscaping$109,7608.0%

These five items make up half the budget. The rest is spread across 30+ smaller items like plumbing ($109K), stucco ($70K), drywall ($50K), and shower doors ($4K).

How It Held Up

The real test of a GMP contract isn't the day you sign it -- it's whether the number holds once the walls are open and the surprises start. Ours did.

MilestoneStatus
Early progress (Feb 2026)~10% complete, 0 change orders
First loan draw (through Apr 30, 2026)~52% complete, 0 change orders
ConstructionCompleted July 2026

We reached the halfway point of a $1.37M build with zero change orders. On a project this size, that's rare -- and it's not luck. It's what good construction documents and a line-item budget buy you: when the plans answer the questions before the framers ask them, the surprises that blow up a budget never happen. The GMP cap gave me a ceiling; the design and the budget kept us from ever getting near it.